ARJUN SAHAYAK PARIYOJNA (U.P.)
Arjun Sahayak Pariyojna envisages use of surplus water of river Dhasan during monsoon to fill existing Arjun, Chandrawal and Kabrai Dam, through feeder channel from Lahchura Dam. Further, the height of Kabrai Dam is to be raised by 9.23m, to irrigate an additional 44,381 hectare.
The Project was approved by TAC of MoWR,RD&GR in October, 2009 and was accorded investment clearance of 806.50 Crore (741.38 Crore for works). The latest completion cost of the project is Rs 2465.68 Crores for works) and expenditure upto March, 2018 is 941.67 Crore. The balance cost of remaining works as on 01.04.2018 is 1524.01 crore. The project was included in AIBP in the year 2009-10 and now it is targeted to be completed by March, 2019. This project is being monitored by M&A Dte, CWC, Agra.
- 1. Project Components:
- 41.60 Km long Arjun Feeder Channel with capacity of 73.60 cumes from Lachura Dam to Arjun Dam
- 31.80 Km long Kabrai Feeder Channel with capacity of 62.32 cumecs from Arjun Dam to Kabrai Dam connecting Chandrawal Dam.
- Raising the height of Kabrai Dam by 9.23 meters thereby increasing the capacity of dam from 1240 ha m to 13025 ha m
- 165.40 Km new canal network which include 50 km new main canal and 115.40 km distributaries and minors to create additional irrigation potential of 44381 ha.
- 2. Benefits
-
a)
Irrigation Potential (IP)
Remarks
Existing
:
15104 ha
CCA of the Project is 149746 ha
AIBP
:
44381 ha
Total
:
59485 ha
IP Created in project (upto 03/2018)
:
12200 ha
(Dry IP, No Irrigation)
IP Utilized
:
NIL
-
- 3.0 Physical and Financial Progress
- A. Physical
-
Land Acquisition
:
50 %
Dam ( Head works)
:
84 %
Main and Branch Canals (Link Chennel)
:
54 %
Distributary System
:
10 %
Water Courses
:
NIL
-
- B. Financial (Amount in Rs Crore)
-
Approved cost estimate as on 04/2012 for AIBP components
:
741.38
Latest Estimated cost of the project for AIBP components
:
2465.6858
Cumulative Expenditure upto 03/2018 (on AIBP)
:
941.67
Balance cost as on 01.04.2018 (on AIBP)
:
1524.01
Budget Outlay for the year 2018-19 (AIBP Component)
:
704.08
-
- A. Physical
- 4. Target Date of Completion: March, 2019
- 5. Major Issues:
-
Land Acquisition
1728.98 ha land is yet to be aquired
R&R
Rehabilitation of 1193 PAPs from 3 villages
Railway Crossing (1 No)
On Kabrai Main Canal
NH Crossing (3 No)
Arjun Feeder (2 Nos) and Kabrai Main Canal (1 Nos)
-
- 6. CA Details (Amount is Rs Crores):
-
Eligible CA as on 01.04.2016 as per PMKSY Guidelines
:
132.408
CA released during 2016-17
:
8.99
CA released during 2017-18
:
2.24
Balance CA to be released
:
121.178
-
- 7: CADWM Details:
-
Target date of completion: March, 2019; Status of inclusion under CADWM Scheme: Included for------ Ha
Area Proposed
Central Share
State Share
Total Cost of CAD Works
CA released (2018-19)
0
0
0
0
0
-