BANSAGAR CANAL PROJECT

The project (UP part) envisages utilization of UP share of water from Bansagar Dam constructed on river Sone in Shahdol district of Madhya Pradesh. Existing annual irrigation in the project is 1.97 Lakh ha in 2.32 Lakh ha of CCA. Aim of the project under AIBP is to provide additional annual irrigation of 1.50 Lakh ha in CCA of 2.32 Lakh ha. Thus, the total irrigation will be 3.47 Lakh ha, thereby increasing the intensity of irrigation from 85% to 150%.
Latest approved cost of works is Rs. 3242.51 crore (PL 2015). The project was included under AIBP in the year 1997-98 and is still ongoing under AIBP (PMKSY part). At present, the project is under Priority-II of 99 prioritized projects and was scheduled to be completed by March, 2018. Ongoing works of the project has not been completed and is likely to be completed by June, 2018.
The project is being monitored by M & A Dte., CWC, Lucknow.

  1. 1. Project Components: The main components of the project are as under:
    • Bansagar Feeder Channel (BSFC): At the end of Common Feeder, lined feeder channel having a length of 71.494 km (including 2.047 km tunnel length) and 46.46 cumec capacity to supply water to Uttar Pradesh. BSFC will outfall in 35.90 km long Adh Nala through which water flows to Adwa Barrage.
    • Adwa Barrage: Adwa Barrage across river Adwa to divert 46.46 cumec of water from Adwa barrage to Meja Dam.
    • Adwa-Meja Link Channel (AMLC): A 25.6 km long and having 46.46 cumec capacity to supply water from Adwa Barrage to existing Meja Dam.
    • Meja-Jirgo Link Channel (MJLC): 16.43 cumec water from Meja Dam shall flow through 74.13 km long MJLC. The MJLC shall feed Baraundha Distributary, Harrai Canal System, Lower Khajuri System etc. and outfall in existing Jirgo reservoir.
    • Meja-Kota Feeder Channel (MKFC): A 3.577 km long and having 9.21 cumec capacity MKFC to augment existing Kota Dy., Upraundh Dy., Belwania Minor etc.
    • Remodelling of old canals (Fed from Meja Dam)
  2. 2.Benefits
    1. a)

      Irrigation Potential

       

       

       

       

      Whole Project

      :

      3.47 Lakh Ha

      CCA of the whole project                   : 2.32 Lakh Ha.

       

      AIBP

      :

      1.50 Lakh Ha

       

      b)

      Annual Irrigation

      :

      3.47 Lakh Ha

      For whole project

      c)

      Drinking Water Supply

      :

      5.67 MCM

      Irrigation Demand: 637.08 MCM (As per TAC Note-2010)

  3. 3.Physical & Financial progress as on 01.04.2018
    1. A.PHYSICAL:
      1. i)

        Head Works

        :

        100 %

        ii)

        Main canal

        :

        98.6 %

        iii)

        Branch canal

        :

        99.6 %

        iv)

        Distributaries

        :

        89.2 %

        vi)

        Irrigation Potential created up to March, 2018

        :

        1.49 Lakh Ha

        Balance IP to be created: 870 Ha.

    2. B.FINANCIAL: (Amount in Rs. crore)
      1. i)

        Approved Cost of works as on 03/2012 for AIBP component

        :

        2842.82 (PL 2008-09)

        ii)

        Latest Revised approved cost of works for AIBP component

        :

        3242.5138 (PL 2015)

        iii)

        Expenditure up to March, 2017 (on AIBP)

        :

        2951.9252

        iv)

        Expenditure during 2017-18

        :

        196.9848

        v)

        Cumulative expenditure up to March, 2018 (on AIBP)

        :

        3118.7604

        vi)

        Balance Cost as on 01.04.2018 (on AIBP)

        :

        123.7534

        vii)

        Budget outlay for the year 2018-19 (on AIBP)

        :

        122.00

  4. 4. Target Date completion: - June, 2018
  5. 5. Issues
    1. 1. Land acquisition

      No land acquisition issues

      2. R&R

      No R&R Issues

      3. Court Cases

      No court cases related issues.

      4. Contractual Issues

      No Contractual Issues

      5. Other Issues

        • Budget provision for 2018-19 is to be made by the State Govt.
        • State Share to be released in full by the State Government immediately.
  6. 6. CA details (Amount in Rs. crore)
    1. i)

      Eligible CA as on 01.04.2016 as per new PMKSY guidelines

      :

      143.5102

      ii)

      CA released during 2016-17

      :

      64.637

      iii)

      CA released during 2017-18

      :

      63.3606

      iv)

      Balance CA to be released as on 01.04.2018

      :

      15.5126

  7. 7. CADWM details:date of Completion June, 2018; Status of Inclusion under the CADWM scheme: Already covered under AIBP
    1. Area Proposed (Lakh Ha)

      Central Share

      State Share

      Total cost of CAD works

      CA released in 2018-19 (Rs. cr)

      CAD works are almost completed under AIBP