MADHYA GANGA PROJECT (STAGE-II), UP
The Madhya Ganga Canal Project Stage-II (U.P.) envisages utilisation of surplus water of river Ganga during monsoon season by diverting it through left regulator of already constructed barrage of Madhy Ganga Pariyojna Ph.-I at Bijnore for development of 1.46 lakh ha Irrigation potential in district Moradabad, Amroha and Sambhal.
The Project was approved by TAC of MOWR,RD&GR in July, 2007 and was accorded investment clearance for Rs 1060.76 crore from planning commission. Cost of the project was revised to 2865.11 crore in year 2012. Further the cost revision on 2016 Price level was done and Fast Track Performa Clearance was accorded by Central Water Commission for 4417.21 crore (4284.46 Crore for works).
- 1. Project Components:
- 66.20 Km long main canal with capacity of 121.80 cumecs
- 50.80 Km long Bahjoi branch with capacity of 60 cumecs.
- 60 Km long Chandausi branch with capacity of 42.60 cumecs
- 1321 km long distributory system
- 2. Benefits:
-
a)
Irrigation Potential (IP)
Existing
:
0.00
CCA 2.25 Lakh ha
AIBP
:
146532 ha
Total
:
146532 ha
IP Created in project (upto 03/2018)
:
NIL
IP Utilized
:
NIL
-
- 3. Physical and Financial Progress
-
A. Physical
-
Land Acquisition
:
65.37%
Dam ( Head works)
:
N/A
Main and Branch Canals (Link Channel)
:
67.39%
Distributory System
:
10.13%
Water Courses
:
NIL
-
- B. Financial (Amount in Rs Crore)
-
Approved cost estimate as on 04/2012 for AIBP components
:
972.49
Latest Estimated cost of the project for AIBP components
:
4284.46
Cumulative Expenditure upto 03/2018 (on AIBP)
:
1014.414
Balance cost as on 01.04.2018 (on AIBP)
:
3270.046
Budget Outlay for the year 2018-19
:
1337.56
-
-
- 4. Target Date of Completion: March, 2019
- 5. Major Issues:
-
Land Acquisition
1946.61 ha land is yet to be acquired
R&R
NIL
Railway Crossing
4 Nos
NH Crossing
4 Nos
Other Issues
NIL
-
- 6. CA Details (Amount is Rs Crores):
-
Eligible CA as on 01.04.2016 as per PMKSY Guidelines
:
92.00
CA released during 2016-17
:
0
CA released during 2017-18
:
0
Balance CA to be released
:
92
-
- 7: CADWM Details:
-
Target date of completion: March, 2019; Status of inclusion under CADWM Scheme: Included